Boeing Slams with $5.4B Loss from 777X Delays

Boeing's Third-Quarter Financial Performance

Boeing, one of the leading aviation companies in the world, has reported a significant financial loss for the third quarter. The company recorded a loss of US$5.4 billion, primarily due to increased costs associated with the delayed certification of its 777X aircraft. This development has had a major impact on the company's overall performance.

Despite this loss, Boeing managed to achieve a 30% increase in revenues, reaching US$23.3 billion. This growth was largely driven by higher commercial plane deliveries compared to the same period in the previous year. However, the financial results were overshadowed by a one-time charge of US$4.9 billion related to the 777X program. The prolonged certification process with U.S. air officials has been a key factor in these challenges.

CEO's Perspective on Progress and Challenges

Chief Executive Kelly Ortberg highlighted some positive developments during the quarter. He pointed to the October approval by the Federal Aviation Administration (FAA) of an increased monthly production rate on the 737 MAX as a sign of progress. Additionally, he noted that Boeing generated positive free cash flow during the quarter, which is a crucial indicator for investors.

However, Ortberg acknowledged that more work is needed to fully recover from a series of safety issues that have affected the company. These issues include two fatal crashes involving the 737 MAX in 2018 and 2019, which have led to increased scrutiny from the FAA regarding new plane certifications.

Delays and Adjustments in the 777X Program

The 777X program has experienced repeated delays. Under the latest adjustments, commercial deliveries are now expected to begin in 2027, which is one year later than the previous target of 2026. Ortberg expressed disappointment over the schedule delay but emphasized that the aircraft continues to perform well during flight testing.

He also mentioned that the company remains focused on completing its development programs and stabilizing operations to fully recover its performance and restore trust with stakeholders. The 777X program has faced challenges due to the lengthy FAA certification process and the impact of the pandemic on airline demand.

Additional Factors Affecting the 777X Program

In 2020, Boeing booked a US$6.5 billion charge on the 777X program, citing the extended FAA certification process and the postponement of airline demand for the jet due to the pandemic. Ortberg clarified that there were no issues with the aircraft’s engine or airframe but noted that the company had "fallen behind" schedule on FAA authorizations for testing.

This delay affected Boeing's ability to "fly and get certification credit," as he explained to CNBC. While there may be a "minor" impact on the process from the ongoing U.S. government shutdown, Ortberg stated that the shutdown did not drive the charge.

Employee Relations and Contract Disputes

In a message to employees, Ortberg mentioned that Boeing's defense operation in St. Louis is "effectively executing our strike contingency plans" following the rejection of the company's latest contract offer by more than 3,000 workers. Local Boeing officials in St. Louis have indicated that the company is accelerating the recruitment of replacement workers and welcoming back employees who cross the picket line.

Union leaders have criticized Boeing for refusing to negotiate in good faith. Meanwhile, shares of Boeing fell 4.1% in early trading, reflecting investor concerns about the company's financial performance and ongoing challenges.